Prior Alternative 6 (originally filed on January 15, 2015)

This alternative, filed with the FERC on January 15, 2015, incorporated a reroute around the St. Luke’s Hospital complex in Bethlehem Township, Pennsylvania between MP 66 and MP 69 and a significant reroute to follow existing power line rights-of-way in New Jersey between MP 90 and MP 110. The re-route in New Jersey necessitated the need to construct a 36-inch diameter, 1.3 mile lateral in Hunterdon County that originates at MP 97.4 and terminates at an interconnect with Algonquin Gas Transmission, LLC (Algonquin) and Texas Eastern Transmission, LP (Texas Eastern) systems.

2014


Pre-Filing

2015


Filing

2016


Review

2017


EIS

2018


FERC Order

2019


Line Operational

Property owners contacted FERC Pre-filing application submitted Public Open Houses

Formal application for PennEast Pipeline filed with FERC

FERC issues their final decision

FERC issues Final Environmental Impact Statement

FERC issues federal approval